DAY-7 20-June-22
EXPECTATION: Foundation brackets and walls to be erected
REALITY: Discovered that not all of the hardware was delivered.
Progress would was quickly be brought to a halt due to lack of material
WHAT IS NEXT: Wait for remaining hardware to be delivered
and arrival of the skid loaded which
will set walls and trusses
Crew to return Tuesday June 21
(Click on Image for larger view)