DAY-8 21-June-22
EXPECTATION: Foundation brackets, walls, and additional framing
REALITY: IT WAS HOT!!! over 100 degrees with "feels like" tempurature.
Primary building posts set, header boards, and side wall purlins installed.
WHAT IS NEXT: Finish setting porch posts, end walls and roof trusses
and possibly porch roof rafters
Crew to return early Wednesday June 22